West Angelas Petroleum (Gas) Pipeline and Stations

Rio Tinto and OSD Pipelines Joint Venture – Newman WA

ec-large
Project Execution Period

August 2012 - March 2014

Contract Value

$138 million

Project Description

The West Angelas Petroleum (Gas) Pipeline (WAPPL) is part of the overall Rio Tinto Iron Ore power system upgrade (PSU330) project that involves the development of new power generation and transmission infrastructure throughout the Pilbara Region of Western Australia.

Scope of Work

Monadelphous and its joint venture partner OSD Limited was awarded the Engineering, Procurement and Construction (EPC) contract for the natural gas pipeline and associated facilities.

The scope consists of the detailed design, approvals, route selection, procurement and construction of the 85km, 16” pipeline from the Goldfields Gas Pipeline to the new power station site within the West Angelas mine. The pipeline traverses difficult terrain with significant hard rock segments.

The design, fabrication and construction of facilities includes an inlet station, main line valve, and delivery station. Other works include the permanent cathodic protection, SCADA and commissioning.

 